The road project starts at SoutoumaSireh (on the Soma – Basse Highway) to the entrance of Gambisara Village in Basse. It is expected to link the communities of SotumaSireh, Gambisara, DembaKunda Koto and DembaKundaKuta (all in the Jimara District) and BasseMannehKunda in the Fulladou District of the Upper River Region. The road also extends to some villages in the Cassamance region of Senegal.
The construction of the said road is in fulfillment of the promise made by the President of the Republic, His Excellency Sheikh Professor Alhaji Dr. Yaya AJJ Jammeh to the community of Gambisara, during the 2015 nationwide “meet the people” tour.
Following an executive directive for the construction of the road, two reputable Contractors were invited to a site visit following which each of them was requested to submit a design and cost
estimate for the construction of the road. Of the invited Contractors, only AREZKI SA made a submission which was subsequently reviewed and approved by NRA. A request for approval on single sourcing of the works to AREZKI SA was sent to the Office of the President to which approval was granted prior to the commencement of implementation activities.
SCOPE OF WORKS
The Contractor shall execute and complete the construction of the 6.2km long, 10m wide road. The works to be executed are described below:
WORKS CONTRACT
Works Contract Information
Contract No | MOTWI/SC/SG-001 |
Contractor | AREZKI GAMBIA SA |
Duration | 6 months |
Notice to commence | August 2015 |
Contract value (Gambian Dalasi GMD) | 155,356,823.03 |
Funding | Government of The Gambia |
An advance payment of GMD 46,607,046.91 representing 30% of the contract sum and an interim payment of GMD 80,150,640.31 was also paid
The earthworks have been successfully executed with the subgrade, sub-base and base layers practically complete from CH 0+000 – CH 6+200. A surplus of about 3cm of laterite was provided for final cutting on the base layer prior to priming.
Pavement layer Composition
Subgrade layer | 100% |
Sub-base layer | 100% |
Base Course | 98% |
Hot-Mix Asphalt Surface | 0% |
CIVIL WORKS (CONSTRUCTION OF CONCRETE STRUCTURES)
There are eight culverts in total including one triple-cell culvert in Gambisara. It was decided to add two additional culverts and three Irish crossings based on observations made during the rainy season regarding the volume of storm water at the selected locations. The construction started with excavation, blinding concrete and casting of the reinforcement mat for the proposed Irish crossings. The construction of all concrete structures is complete with the exception of roadside drains that may be required in Gambissara.
This will entail the protection of the road embankment slopes on high embankments and where stagnation of storm water had been observed during the rainy season.
The use of suitable boulders and mortar for the protection of drainage structures i.e Irish crossings, culverts and drains
Road furniture such as markings and highway signs are to be implemented upon completion of surfacing. Road safety measures to be implemented are expected to include marker posts, kilometer posts and reflective studs.