Lot 8 EPC road project in Gunjur WCR Progress

National Roads Authority > News > Uncategorized > Lot 8 EPC road project in Gunjur WCR Progress

May 13, 2025 / By nraadmin

The 4.5km road project, which starts from the Brusubi-Kartong Highway to the Gunjur seaside. It also branches to the Gunjur Sheikh Ahmad Futi Grand Mosque.
This project is contracted to Green Vision International, and the supervisor is the National Roads Authority (NRA).
The project is a concrete payment and drainage facility on both sides.
The following activities have been carried out during this period.
• Earthworks: 3.7 km out of 4.5 Km completed (84%).
• Subbase: 2.60 Km out of 4.5 km completed (57%).
• Reinforced concrete pavement: Progress is at 57%.
• Culverts out of 2 culverts completed (100%).
• Shallow drains: 2% completed
The overall progress achieved is at 60% completion.