P16 – Kanifing Hospital – GTMI is 0.75km.

National Roads Authority > News > Uncategorized > P16 – Kanifing Hospital – GTMI is 0.75km.

February 25, 2025 / By nraadmin

P16 – Kanifing Hospital – GTMI is 0.75km.
Work progress 99%: Erection of traffic signs started.
P18 – Kololi Senegambia Road Intersection – Touba Sanchaba Road is 1.14km.
Work progress 19%:
– Relocation of water services completed.
– Earthwork is ongoing from CH0+440 to CH0+660.
– Base layer ongoing from CH0+000 to CH0+420.
P19 – Kairaba Avenue (Former IEC) – BJL/Serrekunda Highway (GTTI) is 1.96km.
Work progress 92%:
– P19A1: Pouring concrete for accesses to intersecting roads from CH0+105 to CH0+120 both sides, from CH0+160 to CH0+180 LHS, from CH0+230 to CH0+240 both sides, from CH0+350 to CH0+360 RHS.
– P19A2: Execution of speed humps started at CH0+090.