LOT 2 (PAVIFORT-GAMBISARA-HUTA JV)
The ongoing construction of the 50kms Urban Roads Project, Lot 2 which is contracted to Pavifort-Gambisara-Huta JV, has made substantial progress.
The updates are as follows:
P6 – Kololi Tavern – Bijilo – Brufut is 8.60km
Work progress 57%:
– Erection of solar streetlight poles ongoing from CH0+200 to CH2+200 (71 poles erected) and from CH2+300 to CH4+300 (33 poles erected)
– Road marking ongoing from CH0+000 to CH2+240.
– Spraying prime coat from CH4+620 to CH5+000.
– Relocation of Gamtel services ongoing from CH4+640 to CH5+500.
– Relocation of water services: pressure testing and connection houses ongoing from CH7+140 to CH8+180.

nraadmin
Search
Archive
- April 2026
- March 2026
- February 2026
- January 2026
- December 2025
- November 2025
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
Tags
Recent Posts
- NRA Set to Launch Ebo Town Underground Water Project
- President Barrow Launches 34.9km GIRAV Roads Project in Kombo South, Foni
- Barrow Lays Foundation for Over 45km Agricultural Roads in LRR, WCR
- Barrow Inspects Ongoing Kiang Kabada, Kiang West Roads Projects
- NRA Boss Assures Quality Delivery of GIRAV Roads Project
