Lot 9 EPC (Hawba) road project in Sanyang WCR Progress

National Roads Authority > News > Uncategorized > Lot 9 EPC (Hawba) road project in Sanyang WCR Progress

May 13, 2025 / By nraadmin

The 4.5km road project, which starts from the Brusubi-Kartong Highway to the Sanyang seaside (beach) along the tourist development area
This project is contracted to Zen Construction and Trading Company, and the supervisor is the National Roads Authority (NRA).
The project is a concrete payment and drainage facility on both sides.
The following works were executed during this period.
• Earthworks 4.5km out of 4.5 km completed (100%).
• Subbase 4.5 km out of 4.5 km completed (100%).
• Reinforced concrete pavement 2.42 km out of 4.5 km completed (54.75%).
• Shallow drains yet to start.
The overall progress achieved is 63 % completion.