The 50kms Urban Roads Project Lot 1, which is contracted to SSTP-CSE-AL FAHD JV, progressive update.
Road P1 (2.56 km): GPPC – New Jeshwang (GACEM Junction) – Jokor Junction.
Work progress 97%: No activity for this week.
Road P2 (1.01 km): Kanifing Hospital – Bertil Harding (Methodist) – Estate Road.
Work progress 99%
Road P3 (2.8 km): GPPC Rd – Westfield Jokor – Abuko concrete road
Work progress 73% (delayed by the relocation of the high-voltage poles and water services).
ongoing activities are placing of kerbs, sidewalk pavement and concrete pavement.