Road P7: Touba Sanchaba – Kerr Serign – Sukuta Camping (1.93 km)
Work progress 87%:
Road P8: Bijilo (Bertil Harding) – Sukuta Nemasu – Latrikunda (6.84 km)
P8A1: (2.88 Km)
Work progress 70%:
P8A2: (3.96 Km)
Work progress 12%:
The contractor is working on the earthwork, pavement layer, and relocation of services (NAWEC water pipes and electricity poles, as well as Gamtel pipes).
Road P9: Sukuta – Wullingkama – Brufut – Ghana Town (8.35 km)
Work progress 84%:
Road P20: Kombo Coastal Road (Zion Welding W/shop – Wullingkama Carpark) (1.18 km)
Work progress 98%:
The contractor is now focusing on the erection of traffic signs.