EPC Lot 1 Road Project in URR
The Lot 1 69km project is contracted to Gai Construction.
The project activities commence on 9 project roads out of the total 15 roads. The current progress of the project is 44%. Brief descriptions of the progress made on the various roads are presented below.
1. Basse Manneh Kunda – Demba Kunda – Gambisara Road (12.18km).
The contractor has completed the earthworks, subbase and base except for access junctions. They completed the construction of culverathin 80% completion of the concrete road pavement.
The contractor is yet to begin bituminous surface dressing. The overall progress is at 70%
2. Basse – Dampha Kunda – Tambasansang Road (9.20km).
-Earthworks: – 70% completed
-Culverts: – 25% completed
– Subbase: – 54% completed
-Base: – 30% completed
-Bituminous Surface Dressing: – Not started
-Concrete Road Pavement: – 3%
– Progress: – 36%
3. Chamoi – Dampha Kunda Road (2.66km).
-Earthworks: – 95% completed
-Culverts: – 100% completed
-Subbase: – 100% completed
-Base: – 64% completed
-Bituminous Surface Dressing: – Not started
– Progress: – 43%
4. Angalfuta Road – Reinforced Concrete Pavement (1.75km).
– Earthworks: – 95% completed
– Subbase: – 95% completed
-Concrete Road Pavement: – 95% completed
-Progress: – 98%
5. Manneh Kunda Road – Reinforced Concrete Pavement (1.68km)
-Earthworks: – 52% completed
-Subbase: – 50% completed
– Concrete Road Pavement: – 47% completed
– Progress: – 47%
6. Brikamaba – Boiram – Njoben Road (6.32km)
-Earthworks: – 40% completed
-Culverts: – Not started
-Subbase: – Not started
– Base: – Not started
-Bituminous Surface Dressing: – Not started
-Progress: – 16%
7 Sutukoba – Chamoi Bunda Road, (27km)
-Site clearing and roadbed preparation – 33%
– Sub-grade layer -33%.