The Construction of 50km Urban Roads Project Lot 2 Work Update.
This project is contracted to Pavi-Ford, Gambisara, and Huta JV
Road P6 (8.6 km) that connects from Kololi Tavern – Bijilo – Brufut.
Asphalt has been completed. Shallow drain works are ongoing, and 7km has been executed.
Sidewalk pavement is ongoing with 7.1 km executed. Work progress is 85% completed
Road P7 (1.93 km) which starts from Touba Sanchaba – Kerr Serign – Sukuta Camping. Work progress is 85% completed.
Road P8 (6.84 km) road that connects Bijilo (Bertil Harding) – Sukuta Nemasu – Latrikunda
P8A1 (2.88 Km) with significant work progress of 72% completion.
P8A2 (3.96 Km) road with work progress of 12% completion.
Road P9 (8.35 km) which connects Sukuta – Wullingkama – Brufut – Ghana Town
Work progress is 84% completed.
Road P20 (1.18 km) road that runs through Kombo Coastal Road (Zion Welding W/shop – Wullingkama Carpark.
Work progress is 98% completed. Remaining works include zebra crossings, stop line markings, and traffic signs.