Nuimi Hakalang Road Project Nears Completion Ahead of Inauguration
The Nuimi Hakalang Loop and Secondary Roads Project is nearing completion, with final touches underway ahead of its official inauguration scheduled for next month.
The project, executed by CSE and supervised by consultants Pace & GAMECS, spans 84.5 kilometres and is divided into three main sections. It connects Bunaidu to Kuntair via Chilla Jurunko, and includes vital link roads from Albreda to Fass Omar Saho and Bangally to Bafuloto, all within the North Bank Region (NBR).
Currently, the contractor is focused on three key finishing activities:
• Road Markings: 100km completed out of a total of 253km.
• Drainage Works: 97% completed.
• Kerb Construction: 95% completed.
With an overall progress of 97.8%, the project is on track to meet its deadline, thanks to the tireless efforts of the contractor and stakeholders involved.
This transformative infrastructure initiative is expected to significantly enhance connectivity and economic activity across the region.