Kiang West Roads Project – Phases 1 & 2.
Consultant: Cityscape Associates
Contractor: Gai Construction
Phase 1 (39Km).
One main trunk road of 39km
Road sealing completed.
Road markings completed
Other road furniture: road signs; guard rails; marker posts; cat eyes outstanding.
Phase 2 (48km)
Initially, phase 2 consisted of four roads but now includes 10 roads with access to over 20 villages/ communities.
Activities –
1. Koli Kunda 500m Earthworks and sealing completed. Road furniture installation is outstanding.
2. Jali Roads 2.2Km Earthworks and sealing completed. Road furniture outstanding
3. Keneba to riverside 3.1km. Earthworks and sealing completed. Road furniture and the section of the road’s concrete are outstanding.
4. Manduar – Joulie 11.2Km. Earthworks and sealing completed. Road furniture outstanding
5. Karantaba Gamtel bypass 0.3Km. Earthworks and sealing completed. Road furniture outstanding.
6. Karantaba center linking: Phase 1; Janneh kunda; Medina & Burong. Earthworks completed. Road concrete is over 95% completed
7. Karantaba to Medina (2km). Earthworks and sealing completed. Road furniture outstanding
8. Kantong kunda (1.2km). Earthworks and sealing completed. Road furniture and a section of road concrete are outstanding
9. Kemoto – Janneh Kunda – Karantaba – Missira Tenda (17km). Earthworks and sealing completed. Road furniture outstanding.
10. Manduar – Tankular (8.1km) Earthworks and sealing completed. Road furniture outstanding.
11. Manduar – Gissay (5.4km). Earthworks completed. 40% sealing done
General Remarks
Significant progress on road sealing since the last report. With the expected new concrete team, work on drainage structures will improve in the coming weeks.
Overall progress:
Phase 1 – 95%
Phase 2 – 90%