Construction of 50kms Urban Roads Project Lot 2 progressive update
The project for ongoing construction is contracted to PAVIFORT-GAMBISARA-HUTA JV)
Road P6: Kololi Tavern – Bijilo – Brufut (8.6 km).
The current work progress is 85%. The contractor has already completed 8.3km of asphalt. The shallow drain is almost completed (8 km executed), and the sidewalk pavement is almost completed (7.1 km executed).
Road P7: Touba Sanchaba – Kerr Serign – Sukuta Camping (1.93 km).
The current work progress is 85%. The contractor has already completed the asphalt work, and the sidewalk pavement is almost completed. What is remaining is road markings, traffic signs and the erection of streetlighting poles.
Road P8: Bijilo (Bertil Harding) – Sukuta Nemasu – Latrikunda (6.84 km).
In P8A1: (2.88 Km)
The work progress is 72%.
– 2,27 km asphalted
– 2,23 of sidewalk paved
– Earthwork ongoing.
In P8A2: (3.96 Km)
The work progress is 13%.
-400m asphalted
-Base and sub-base layers are ongoing
-Earthworks ongoing
works affected by the rains
Road P9: Sukuta – Wullingkama – Brufut – Ghana Town (8.35 km).
The work progress is 86%. The delay of work is affected by the rain.
The contractor has achieved 7.5km of both the shallow drain and sidewalk pavement
Road P20: Kombo Coastal Road (Zion Welding W/shop – Wullingkama Carpark (1.18 km).
The work progress is 98%. The remaining work includes zebra and stop line markings, and traffic signs.