EPC LOT 4 Road Project in the West Coast Region.#
The Lot 4 roads project, is located in the Western Region and constitutes part of the country’s Western transportation link.
The Project consists of the construction of four sections for a total length of approximately 20.7 km.
The Contractor for this project is SOMAGEC, while GAMECS is the Consultant
The project consists of the construction of twelve (4) roads, approximately 20.7km in total length and all the roads are currently on base level.
KALAGI TO BUNDALI) (10.20 KM)
The contractor has currently achieved 98% on the earthworks, and has entirely completed the reinforced concrete pavement (Irish crossing), drainage structures (culverts) and erosion control (Irish crossings and culverts) respectively.
JOREM NEMA KUNDA – JOREM BUNDA KUNDA – (1.45KM).
The contractor has currently achieved 98.8% on the earthworks, and has entirely completed the reinforced concrete pavement (Irish crossing), drainage structures (culverts) and erosion control (Irish crossings and culverts) respectively.
SANGAJOR – DASILAMI – 5.78KM
97% of the earthworks have been completed, while the reinforced concrete pavements (Irish crossing), drainage structure (culverts), and erosion control (Irish crossings and culverts) have all been completed.
KANFENDA –MANDINA – 5.10KM
The contractor has entirely completed the reinforced concrete pavement (Irish crossing), drainage structures (culverts) and erosion control (Irish crossings and culverts) respectively. They have also achieved 95.8% of the earthworks.
Overall work progress is 73.2%.
GIBORO-SOHM 13KM
As the project is in an early stage, the Contractor is currently on the clearing and grubbing stage.