Lot 3 Kiang Kabada Road Project
The 102km road project is contracted to Long Jin Construction (a Chinese company), and Gamecs (a Gambian company) is the Consultant.
The project consists of the construction of twelve (12) roads, approximately 102 km in total length and all the roads are currently on base level.
The contractor is actively working on five of the 12 project roads. Overall work progress is estimated at 62.2%.
1. Njolfen Toranka Bantang Kolior Sulah (5.728km)
• Earthworks- 96.8%.
• Reinforced concrete pavements (Irish crossing) – COMPLETED
• Drainage structure (culverts) – 1 out of 3 COMPLETED.
• Surface treatment – 31.25%
• Prime coat -30%
2. Gambia Border – Sare Sajo – Jatta Kunda – Nemakuta (8.545km)
• Earthworks – 93%
• Reinforced concrete pavements Irish crossing) – 88%
3. Nioro – Sibito – Sare Suna – Kundong Fula Kunda (7.336 KM).
• Earthworks – 97%
• Surface treatment – 13.6%
• Reinforced concrete pavements Irish crossing) – 90%
• Drainage structures (Culverts) – COMPLETED
• Erosion Control for culverts – COMPLETED
4. Kwinella – Wellingara – Tabanani – Madina – Nioro – Sare Sajo – Tabanani – Madina – Nioro – Sare Sajo – Njolfen Alignment (18. 880 km).
• Earthworks – 95%
• Reinforced concrete pavements Irish crossing) – 92%
• Drainage structures (Culverts) – COMPLETED
• Surface treatment – 45.2%
• Prime coat – 34.4%
• Surfacing (Pavement layer) – 21.2%
• Erosion Control – COMPLETED
5. Sare Sajo – Sare Ndalla – Toranka Bantang – Sare Pateh – Yoro Jula (6.296km).
• Earthworks – 98%
• Reinforced concrete pavements Irish crossing) – 88%