NRA Technical Team Inspects Ongoing Kuntaya Culvert Construction in North Bank Region
As part of its ongoing nationwide inspection of agricultural road infrastructure projects, a technical team from the National Roads Authority (NRA) on Friday, 31st July 2026, visited the Kuntaya Triple Cell Culvert construction site in the North Bank Region (NBR) to assess the progress of works.
The culvert project, being implemented by Pinnacle Group JV Heritage Holdings, is a key component of efforts to improve rural connectivity and ensure year-round access for communities and agricultural transport.
The inspection team observed that the contractor has successfully completed the concrete floor slab and is currently undertaking steel reinforcement works for the top slab. According to the contractor, the casting of the top slab is scheduled for either Sunday or Monday, subject to favourable weather conditions.
The NRA technical team expressed satisfaction with the progress made so far and reaffirmed the Authority’s commitment to closely monitoring ongoing projects to ensure quality standards are maintained and construction is completed on schedule.