P10 – Junctionba – Hermann Gmeiner Road Amsterdam is 1.26km
Work progress 99%: remains the erection of traffic signs.
P12 – Rev. J.C Fye road is 2.31km.
Work progress 25%: No activity for this week (relocation of water services interrupted).
P13 – Sukuta Health Center – Kololi/Senegambia Road Intersection (3.25km).
Work progress 38%: (delayed by the relocation of the high voltage poles and water services)
– Precasting of kerbs.
– Shallow drain is ongoing from CH1+030 to CH1+310 LHS, from CH1+400 to CH1+480 LHS and from CH1+360 to CH1+490 RHS.
P15 – Bundung Highway is 2.68km.
Work progress 99 %: remains the erection of traffic signs.
– Execution of speed humps started at CH0+440, CH0+720 and CH0+940.

nraadmin
Search
Archive
- May 2026
- April 2026
- March 2026
- February 2026
- January 2026
- December 2025
- November 2025
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
Tags
Recent Posts
- President Barrow inspects ongoing road projects
- Barrow opens 12km roads project in Madiana
- Brufut – Madiana – Banyaka – Kunkujang Mariama Road Project to Be Inaugurated Tomorrow
- NRA Holds Sensitisation Meeting on Ebo Town Dewatering Project
- NA Select Committee Impressed with Progress on Government-Funded Roads Projects
