P16 – Kanifing Hospital – GTMI is 0.75km.
Work progress 99%: Erection of traffic signs started.
P18 – Kololi Senegambia Road Intersection – Touba Sanchaba Road is 1.14km.
Work progress 19%:
– Relocation of water services completed.
– Earthwork is ongoing from CH0+440 to CH0+660.
– Base layer ongoing from CH0+000 to CH0+420.
P19 – Kairaba Avenue (Former IEC) – BJL/Serrekunda Highway (GTTI) is 1.96km.
Work progress 92%:
– P19A1: Pouring concrete for accesses to intersecting roads from CH0+105 to CH0+120 both sides, from CH0+160 to CH0+180 LHS, from CH0+230 to CH0+240 both sides, from CH0+350 to CH0+360 RHS.
– P19A2: Execution of speed humps started at CH0+090.

nraadmin
Search
Archive
- April 2026
- March 2026
- February 2026
- January 2026
- December 2025
- November 2025
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
Tags
Recent Posts
- NRA Set to Launch Ebo Town Underground Water Project
- President Barrow Launches 34.9km GIRAV Roads Project in Kombo South, Foni
- Barrow Lays Foundation for Over 45km Agricultural Roads in LRR, WCR
- Barrow Inspects Ongoing Kiang Kabada, Kiang West Roads Projects
- NRA Boss Assures Quality Delivery of GIRAV Roads Project