P20 – Kombo Coastal Road (Zion Welding W/shop – Wullingkama Carpark is 1.18km
Work progress 90%:
– Erection of solar streetlight poles ongoing from CH0+000 to CH1+180 (40 poles erected).
P11 – (Bijilo Site Access) is 0.9km
Work Progress 0%: Work not yet started.

nraadmin
Search
Archive
- August 2026
- July 2026
- June 2026
- May 2026
- April 2026
- March 2026
- February 2026
- January 2026
- December 2025
- November 2025
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
Tags
Recent Posts
- President Barrow Launches 36.1km of Road Projects in West Coast Region
- President Barrow Inspects Progress on Kiang Kabada Road Project
- Barrow Inaugurates Kusun–Garawol Road, Launches New 24km Project
- Barrow Inaugurates Karantaba–Reneru–Fitu Fulla Road Project
- President Barrow Launches Connect Gambia Lots 6 & 7, Inaugurates Njau Loop Road