The Construction of 50km Urban Roads Project Lot 1 Work Update.
This project is contracted to SSTP, CSE, and AL FAHD JV.
Road P1 ( 2.56 km) road from GPPC – New Jeshwang (GACEM Junction) – Jokor Junction.
Work progress is at 98% completed. The contractor is working on the remains which include zebra crossings, stop line markings, information signs, and some streetlighting poles.
Road P2 ( 1.01 km) road that connects Kanifing Hospital – Bertil Harding (Methodist) – Estate Road.
This road’s work progress is 99% completed with remaining work on zebra crossings, stop line markings, and information signs.
Road P3 (2.8 km), which runs from GPPC Rd – Westfield Jokor – Abuko, is a concrete road.
Work progress on this road is at 73% completion, which is caused by a delay in the relocation of the high voltage poles and water services.
Current works include the placement of Kerbs, sidewalk pavement, and concrete pavement.
Road P5 (3.36 km) road that runs from Sukuta to Latrikunda Sabaji.
Pavement of the sidewalk and parking area is almost completed. Remaining works include road marking, traffic signs, and the erection of streetlighting poles. Work progress is 90% completed.
Road P10 (1.26 km) road that runs from Junctionba – Herman Gmeiner Road in Amsterdam.
Work progress is 99% completed. Remaining works include zebra crossings, stop line markings, and information signs.
Road P12 (2.31 km) Rev. J.C. Fye Road.
Current works include the placement of Kerbs, an ongoing shallow drain, and 1.4 km out of 2.31km has been asphalted.
Road P13 (3.25 km) from the Sukuta Health Centre – Kololi/Senegambia Road Intersection.
Work progress is at 83% completion.
Asphalt work is completed. The remaining works include sidewalk pavement, road marking, traffic signs, and the erection of streetlighting poles.
Road P15 (2.68 km) road on Bundung Highway.
Work progress is 99 % with a remainder of zebra crossings, stop line markings, and information signs.
Road P16 (0.75 km) from Kanifing Hospital – GTMI
Work progress is 99%, the remaining work includes zebra crossings, stop line markings, and information signs
Road P18 (1.14 km) road from Kololi Senegambia Road Intersection – Touba Sanchaba Road.
Work progress 88% completed, and the remaining works include road marking, traffic signs, and the erection of streetlighting poles.
Road P19 (1.96 km) from Kairaba Avenue (Former IEC) – BJL/Serrekunda Highway (GTTI).
Work progress is 99% completed. Remaining work includes zebra crossings, stop line markings, and information signs