The Construction of 50km Urban Roads Project Lot 2 Work Update.
This project is contracted to Pavi-Ford, Gambisara, and Huta JV
Road P6: Kololi Tavern – Bijilo – Brufut (8.6 km).
Work progress 90%: 8.35 km asphalted, shallow drain almost completed (8 km executed), sidewalk pavement almost completed (8 km executed). Remains completion of streetlight, traffic signs and road markings.
Road P7: Touba Sanchaba – Kerr Serign – Sukuta Camping (1.93 km).
Work progress 92%: Asphalt completed, sidewalk pavement almost completed. The outstanding works are traffic signs and the erection of solar streetlight poles.
Road P8: Bijilo (Bertil Harding) – Sukuta Nemasu – Latrikunda (6.84 km)
P8A1: (2.88 Km)
Work progress 88%: Asphalt pavement completed, 2,23 km of sidewalk paved, erection of streetlighting poles ongoing (31 poles erected). The remaining work is the erection of traffic signs and road markings.
P8A2: (3.96 Km)
Work progress 73%: 1.8 km asphalted, pavement layers completed, sidewalk pavement ongoing (1.4 km executed) and placing of Kerbs ongoing (1.4 km placed).
Road P9: Sukuta – Wullingkama – Brufut – Ghana Town (8.35 km)
Work progress 92%: Asphalt pavement completed, 8.2 km of drains and shallow drains executed, 8.2 km of sidewalk pavement completed. The remaining works include completion of solar streetlighting, traffic signs and road markings.
Road P20: Kombo Coastal Road (Zion Welding W/shop – Wullingkama Carpark (1.18 km)
Work progress 98%: the outstanding works are zebra and stop line markings, and traffic signs.