The ongoing construction of the 50kms Urban Roads Project, which is contracted to SSTP-CSE-AL FAHD JV, has made significant progress.
The updates are as follows:
P1, which starts from GPPC – New Jeshwang (Gacem Junction) to Jokor Junction, is 2.56km.
Work progress is currently 87%, and the contractor is currently working on the pavement layer on the extension to the swamp.
P2 – Kanifing Hospital – Bertil Harding (Methodist) – Estate Road is 1.01km.
Work progress 99%: (remains the erection of traffic signs).
P3 – GPPC Rd – Westfield Jokor – Abuko concrete road is 2.8km.
Work progress 18%: (delayed by the relocation of the high voltage poles and water services).
– Placing of Kerbs ongoing from CH2+120 to CH2+160 on both sides.
– Concrete pavement from CH2+070 to CH2+270 RHS and 2+340 to CH2+360 RHS.

nraadmin
Search
Archive
- April 2026
- March 2026
- February 2026
- January 2026
- December 2025
- November 2025
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
Tags
Recent Posts
- NRA Set to Launch Ebo Town Underground Water Project
- President Barrow Launches 34.9km GIRAV Roads Project in Kombo South, Foni
- Barrow Lays Foundation for Over 45km Agricultural Roads in LRR, WCR
- Barrow Inspects Ongoing Kiang Kabada, Kiang West Roads Projects
- NRA Boss Assures Quality Delivery of GIRAV Roads Project